UK: Connections, Reform and Clean Power
NESO publishes Clean Power 2030 advice to UK Government, as it consults on critical reform methodologies
November 07, 2024
UK: Connections, Reform and Clean PowerNESO publishes Clean Power 2030 advice to UK Government, as it consults on critical reform methodologiesNovember 07, 2024 On 5 November 2024, the National Energy System Operator (NESO) published its “Clean Power 2030” (CP30) advice to the UK Government, and launched a consultation on its proposals for aligning the reformed connections process with strategic energy plans (both the CP30 and the first Strategic Spatial Energy Plan). Clean Power 2030In its CP30 advice, NESO recognises that achieving clean power is challenging, but the ambition can be met by 2030. The report highlights two “clean power pathways”:
These two clean power pathways are intended to ensure that Great Britain becomes a net exporter of power, and reduces the proportion of unabated gas generation below 5%. Both pathways centre on offshore wind as the “bedrock” of the new system, with NESO’s advice being that the clean power system must be based on offshore wind, as it is the only clean option available at the scale required by 2030. Other technologies, such as nuclear, will play an important role in the future delivery of clean power, given their reliability and non-reliance on weather conditions. Recognising the importance of security and flexibility, the pathways also highlight the benefits of battery capacity, which needs to increase to around 23-27GW by 2030. Although there are plenty of projects in the pipeline, delivery of these projects relies on (and is at risk of) the reforms to the connections queue, as well as resolution of planning issues and the availability of revenue opportunities. NESO highlights that short-duration BESS is the starkest example of over-supplied technology based on CP30-alignment. For long-duration energy storage (LDES), however, the pipeline for options ready to deploy by 2030 is limited. Deployment of LDES technologies has recently been the subject of a Government consultation response (see ES Briefing), and further information is expected on the detail of the LDES cap and floor regime during Winter 2024. Alongside the challenges of managing demand and supply, balancing flexibility with security, and delivering a connections reform that will quicken the connections queue, there are operability issues that will also need to be addressed to ensure the system can be operated with zero carbon. NESO advises that changes within the Control Centre and support functions are needed to enable the operation of a clean power system in 2030, with a need for further investment in digitalisation and artificial intelligence to realise this. Addressing some of the barriers faced by the energy industry, NESO also highlights some of the key enablers for CP30, including greater investment, planning and consenting, and of course connections reform. It is now with the UK Government to finalise the CP30 plan, taking account of NESO’s advice, which is expected later this year. Support from Ofgem and DESNZIn an open letter to industry, also published on 5 November 2024, the Department for Energy Security and Net Zero (DESNZ) and Ofgem have demonstrated their support for the alignment of strategic planning with connections reform. The letter highlights the need for certainty, with strategic plans setting out decisions about the different technologies needed in different geographical locations, as well as the importance of ensuring the system is flexible enough to enable competition and respond to future needs or changes. Ensuring demand users can connect to the network will require investment in data centres and gigafactories, the electrification of industrial centres, road transport and ports, and the building of new housing, prisons or hospitals. With much of the current connections reform focus being on transmission connections, DESNZ and Ofgem recognise the importance of not letting reform of distribution connections “fall by the wayside”, and ensuring the new connections process is implemented consistently by all network companies. Consultation on connection methodologiesNESO aims to align the connections process to the government’s Clean Power 2030 Action Plan, and is consulting on its proposals, which include:
In its consultation document, NESO outlines a draft plan demonstrating the key milestones to implement the connections reform process, indicating that a decision on the methodologies and the required modifications to industry codes will be made Q1 2025 (subject to change). Implementation of the connections reform is expected to begin from Q2 2025 with Gate 1 projects being issued offers. For those interested in responding, the consultation closes at 5pm on 2 December 2024. Capacity Commitment FeeAnother key aspect currently being consulted on is the proposal to introduce a “Capacity Commitment Fee” (CCF) of £20,000/MW, which would need to be secured (in the same way as Cancellation Charges) once a project accepts its Gate 2 offer. NESO has a Call for Input out currently on this, seeking industry input on the need / quantum in light of other aspects of the reforms. The details were published in the 11 October 2024 presentation in the Transmission Charging Methodologies Forum and CUSC Issues Steering Group. To avoid “excessive security requirements”, the existing Cancellation Charge Secured Amount will be net off from the CCF, with developers being liable for security of the greater amount between the two cancellation charges. NESO is proposing that it would be able to draw on the security if a developer, having accepted its Gate 2 offer, leaves the queue before achieving User Progression Milestone 7: Project Commitment, fails to deliver one of its milestones, or reduces its original transmission entry or developer capacity. Think of it like a minimum security requirement until FID, at which point Users would switch to cost-reflective Cancellation Charges. Currently it appears this is only envisaged for generation connections (not demand-only, which is on Final Sums methodology, rather than Cancellation Charge methodology under Section 15 of the CUSC). The deadline for the Call for Input is 22 November 2024. This proposal will then be considered further by way of a code modification. How do I keep track of the developments?The Connections Reform developments are coming thick and fast, with numerous consultations now in flight, and we know that trying to keep track of it all can be challenging. If you want to know more, or have any particular concerns, get in touch with a member of our team who will be able to help you navigate your way through the latest developments. For more information on the proposed changes, catch up on our latest webinar:
Latest Insights
Latest News
Latest Events
legal updates June 05, 2026 Cyber Resilience Landscape – An Update to Practical Implementation legal updates June 05, 2026 The UK Employment Rights Act: zero hours and low hours contract provisions legal updates June 04, 2026 FS+ Country Updates – May 2026 legal updates June 04, 2026 UK Real Estate Round Up May 2026 client news June 04, 2026 Advising Howden Joinery Group plc on £390m DIY Kitchens acquisition client news June 04, 2026 Next stop, public ownership: Eversheds Sutherland advises DfT on GTR transi... client news June 03, 2026 A blueprint for growth: Eversheds Sutherland supports Leonard Design Group ... firm news June 01, 2026 Eversheds Sutherland strengthens restructuring offering with senior partner... virtual UK employment law training June 09, 2026 1pm - 4pm (BST) Virtual virtual Education Webinar - Occupational Stress : Preventing Suffering, Enhancing W... June 10, 2026 11:00AM - 12:00PM virtual Nordic (Denmark, Finland, Norway and Sweden) employment law training June 16, 2026 12.45pm - 4pm (BST) Virtual virtual Education Webinar - Equality, diversity and inclusion: current developments... June 17, 2026 11:00AM-12:00PM |