Germany: Federal Government reaches agreement and decides to alleviate burdens for businesses and data centres
July 13, 2026
Germany: Federal Government reaches agreement and decides to alleviate burdens for businesses and data centresJuly 13, 2026 Why should I read this?On 24 June 2026, the German Federal Government (Bundeskabinett) adopted the draft “Act to Accelerate the Implementation of the Energy Efficiency Directive” (Entwurf eines Gesetzes zur Beschleunigung der Umsetzung der Energieeffizienzrichtlinie). The bill proposes significant amendments to the Energy Efficiency Act (Energieeffizienzgesetz, EnEfG) of 13 November 2023, namely to the rules governing data centres (Rechenzentren). It will bring substantial alleviations for building and operating data centres and also remove burdens from other businesses. Despite the name of the draft act, requirements for data centres pursuant to the EnEfG will still significantly exceed those of Directive 2023/1791 on energy efficiency. What do I need to know?Among various important changes provided by the draft, we would like to note the following:
These targets will be relaxed to 1.6 or lower for data centres operating before 1 July 2026, to be achieved by 1 July 2027, and to 1.4 or less by 1 July 2030. Data centres becoming operational from 1 July 2026 will still have to reach a PUE of no more than 1.2.
The draft will bring two changes to these exemptions. First, the "agreement" exemption (ground 2) will no longer be contingent on an investment plan and agreement on cost-sharing (Investitionsplan sowie Regelung zur Tragung der Kosten). The municipality or heating network operator will just have to declare its “concrete intention” to build or permit heat networks enabling compliance within ten years. Second, the operator will also be exempt if there is no technically and economically feasible connection to an existing or planned district heating network. This has to be demonstrated by a cost-benefit analysis as provided under new § 16(3) and (4). In any case, data centres will have to be built so as to provide sufficient space for future heat supply infrastructure.
when the operator plans or substantially modernizes the respective facility. Data centres whose waste heat is already being used for district heating, space heating, hot water, or other building purposes will be exempted. The cost-benefit analysis will have to comply with Annex XI of Directive 2023/1791. Open Questions
What should I do next?Data centre operators and investors in Germany should monitor the legislative process for potential further amendments in the parliamentary process and benefit from the opportunities which reduced regulatory burdens entail. Latest InsightsLatest News
Latest Events
legal updates July 20, 2026 Industrials Unpacked #1: Supply Chain Contracts legal updates July 17, 2026 EU MISP reforms: ESMA to supervise more firms legal updates July 17, 2026 EU Forced Labour Regulation legal updates July 16, 2026 Trump v Slaughter: What the US Supreme Court’s ruling means for transatlant... firm news July 10, 2026 Eversheds Sutherland advises OCBC on the landmark secondary dual listing of... client news July 10, 2026 Setting sail: Eversheds Sutherland advises senior management of D-Marin on ... client news July 09, 2026 Eversheds Sutherland advises Costello Medical on transition to employee own... firm news July 01, 2026 Eversheds Sutherland lands lateral partner-led Paris Funds team, as its wid... virtual UAE - Employment law in the Dubai International Financial Centre September 10, 2026 9.30am - 1.30pm (GMT) Virtual in-person Managing AI use in the workplace: what every UK HR team needs to know September 10, 2026 9.30am - 1.00pm (BST) London, United Kingdom in-person Basic foundations of US employment law September 17, 2026 9.30am - 4.30pm (GMT) London, United Kingdom in-person 2026 BDC Roundtable September 23, 2026 Washington DC, United States |